The site before clearing
|

The site before clearing
|

Clearing and compacting
for floating foundations |

Fence construction
|

|
|

Septic tank construction
|

Foundation reinforcing
construction |

Foundations & inner walls
foundations |

Shuttering, welded mesh &
waterproofing |

Foundation reinforcing &
waterproofing |
|

Arrival of ready-mix
concrete |

Arrival of ready-mix
concrete |

Spreading ready-mix
concrete |

Levelling floors
|

The builder controlling
operations |
|

Bedroom walls begin
|

Bedroom
|

Bedroom
|

The builder and the
balloon
man |

Lounge walls begin.
Tania,
Lorna, Doug |
|

Lounge walls progress
|

Lounge walls progress
|

Verandah pillars go up
|

Initial balloon inflation
|

Hi-tech discussions
in progress |
|

Laying the first bricks
against the balloon |

Balloon deflated after
first
day's brick laying |

Roof construction on
bedroom dome |

Roof after first day's
bricklaying |

Roof after first day's
bricklaying |
|

Bedroom dome almost
completed |

Bedroom dome almost
completed |

|

Laying critical cap on
dome
|

Laying critical cap on
dome
|
|

Lounge wall construction
|

Lounge wall construction
|

Bedroom dome almost
completed |

Bedroom dome completed
|

Balloon hanging from roof
-cap support |
|

Lounge dome almost
completed |

Lounge dome bagwashed
|

|

Lounge & bedroom
domes completed |

Lounge undercoated |
|

Lounge/Kitchen divider
|

Painting undercoat
|

|

Colour swatched
|

Undercoat completed
|
|

Verandah started
|

|

|

Double Carport |

Laying cement slabs on verandah |
|

Kitchen security door
|

Bathroom table slab
|

Lounge/kitchen dome
|

Tiling begins
|

Lounge security gate
|
|

Tiling in bedroom
|
|
|
|
|
|
Completed House
Click on any image to download/enlarge |
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
|